Policy

Automatic Calculation

Specifies that calculations should be done automatically as soon as a change is made. If you enable this setting, calculations will be made after every change to the project. If you disable or do not configure this setting, the user's default setting is used.

Policy
PackMicrosoft Office
CategoryMicrosoft Project 2016 / Project Options / Calculation / Calculation options for Microsoft Project
Policy ID7a67103e04da
Internal nameL_PjAutoCalc

Registry

Copy registry mappings

HKCU\software\policies\microsoft\office\16.0\ms project\options\calculation\auto calc (enabled) = 1
HKCU\software\policies\microsoft\office\16.0\ms project\options\calculation\auto calc (disabled) = 0

Policy notes

Specifies that calculations should be done automatically as soon as a change is made. If you enable this setting, calculations will be made after every change to the project. If you disable or do not configure this setting, the user's default setting is used.

Related policies