Policy

Baseline for Earned Value calculations

Specifies the baseline that is used to measure project performance using earned value analysis. If you enable this setting, Project will calculate earned value using the baseline you specified. If you disable or do not configure this setting, the user's default setting is used.

Policy
PackMicrosoft Office
CategoryMicrosoft Project 2016 / Project Options / Calculation / Calculation options for 'Project1' / Earned Value options for Project1
Policy IDef81b09b2df8
Internal nameL_PjEVBaseline

Registry

Copy registry mappings

HKCU\software\policies\microsoft\office\16.0\ms project\options\calculation\evbaseline

Policy notes

Specifies the baseline that is used to measure project performance using earned value analysis. If you enable this setting, Project will calculate earned value using the baseline you specified. If you disable or do not configure this setting, the user's default setting is used.